January - 1 articles
March - 1 articles
May - 2 articles
February - 3 articles
May - 2 articles
June - 4 articles
July - 1 articles
August - 1 articles
September - 1 articles
November - 1 articles
December - 3 articles
February - 2 articles
March - 1 articles
April - 3 articles
May - 3 articles
June - 7 articles
August - 3 articles
October - 3 articles
November - 2 articles
February - 1 articles
March - 1 articles
April - 2 articles
May - 4 articles
June - 2 articles
August - 5 articles
September - 4 articles
October - 6 articles
December - 2 articles
January - 1 articles
February - 2 articles
March - 1 articles
April - 10 articles
May - 3 articles
June - 5 articles
July - 1 articles
August - 3 articles
September - 2 articles
October - 5 articles
November - 1 articles
December - 5 articles
December - 1 articles
Date: 05th December 2008
The Stag 2 report considered a range of possible options, including; reinstating the existing disused railway line, and establishing a straightened track alignment between Thornton Junction and Windygates.
Reinstatement of the existing route, at a cost of £48 million, has been identified as the most cost-effective option. It will also minimise the project’s environmental impact, by confining work to a pre-existing rail bed.
The reinstated route will feature two new stations at Leven and Cameron Bridge, with freight services also operating from Cameron Bridge.
A report will now be submitted to Transport Scotland, with the aim of obtaining agreement to progress the project through the railway industry’s Guide to Railway Investment Projects (GRIP) stages. This will involve Transport Scotland and Network Rail as key stakeholders.
SEStran Chair, Cllr Russell Imrie said:
“SEStran was already aware that significant local support existed for the reintroduction of rail services at Levenmouth. This report clearly shows that there is also a business and environmental case”.
“It is estimated that the service would carry up to 500,000 passengers a year, many of whom would otherwise have travelled by car. This number also includes a significant number of new-generated journeys”.
“The reinstated service will make Levenmouth far more attractive as a place to work and do business and has the potential to play an important role in the economic revival of the area. At the same time it will contribute towards SEStran’s goal of cutting congestion on the region’s roads and reducing our carbon footprint”
SEStran - South East of Scotland Transport Partnership - is one of seven new Statutory Regional Transport Partnerships (RTP) created by the Transport (Scotland) Act 2005 and is a partnership of eight local councils covering the Borders, East Lothian, West Lothian, Midlothian, Edinburgh, Fife, Falkirk and Clackmannanshire.
For further information, please contact:
Andrew Dougal, SEStran Communications Officer
T: 0131-524-5161
M: 07889-010-291
E: Andrew.dougal@sestran.gov.uk
Notes :
1.LEVENMOUTH SUSTAINABLE TRANSPORT STUDY
1. BACKGROUND
1.1. Earlier this year SEStran appointed Scott Wilson Transportation consultancy to undertake a multi-modal study into improving transport facilities to/from Levenmouth in Fife.
1.2. A progress report was submitted to the last Board meeting and this report outlines the final outcome of the study.
1.3. The executive summary is attached to this report and a hard copy will be made available in the members’ area in the SEStran office. The study report will also be posted on the SEStran website.
2. KEY FINDINGS
2.1. The most favourable option was to utilise the existing rail alignment rather than constructing in part a new alignment that would have resulted an increase in journey speed.
2.2. Two stations should be provided at Leven and Cameron Bridge (with freight facilities also provided at the latter site) and would be served by extending the current hourly service to Kirkcaldy.
2.3. The cost of the scheme is estimated in the region of £48 million at 2008 prices (£87 million at 2016 prices) and this includes contingencies, risk costs and optimism bias.
2.4. The Benefit to Cost Ratio BCR was estimated at a relatively high 1.5, with a Net Present Value (NPV) of £21 million, i.e. the overall benefit to society by implementing this scheme would exceed costs by this amount.
2.5. The level of usage is estimated initially at around 350,000 which will have transferred either from car or bus or would have extended their rail journey by joining at Leven or Cameron Bridge rather than Kirkcaldy.
2.6. A probable further increase in generated traffic (due to new generated journeys) of around 42% can be assumed (based on experience from Alloa). This would increase the BCR to a 1.99 and the NPV to £45 million.
2.7. Additional passengers would use the service should also the hourly Cowdenbeath service be extended to Leven to form a combined half-hourly service. However, this would result in lower estimated BCR and NPV values due to assumed doubling of additional operating costs. Should there be more efficient ways to schedule such an operating scenario – with corresponding lower operating costs – this may be the ‘best’ option.
3. NEXT STEPS
3.1. A meeting with Transport Scotland has been arranged for later in the month – with the aim of obtaining agreement to progress this project through the railway industry’s Guide to Railway Investment Projects (GRIP) stages – which would involve Transport Scotland and Network Rail as key stakeholders.
3.2. Approximately 25k this year’s SEStran revenue budget for the Levenmouth project should be available as a possible contribution towards the next step of the project.
4. RECOMMENDATION
It is recommended that the Board:-
4.1 notes the content of this report
4.2 approves the findings and recommendations of the report, and
4.3 agrees that the Director opens discussions with Transport Scotland and other relevant parties to progress the project.
Trond Haugen
Advisor to SEStran
28 November 2008
Policy > Implications, Will deliver towards SEStran RTS
Financial > Implications, Work within budget
Race Equalities > Implications, None
Gender Equalities > Implications, None
Disability Equalities > Implications, None
2.
Executive Summary
E.1 Introduction
E.1.1 SEStran has developed a Regional Transport Strategy (RTS), which has identified several projects for taking forward for potential development, categorised within identified strategic corridors for prioritising investment. The Queensferry and the Central Fife were two such corridors identified, both of which involve heavy commuter flows to Edinburgh. Part of the solution for these corridors would be to increase public transport provision between Fife and Edinburgh, and an important scheme in this respect would be the introduction of passenger services to Levenmouth, whilst also increasing the share of the freight transport market carried by rail. Consequently, South East Scotland Transport Partnership (SEStran) appointed Scott Wilson to carry out a STAG–based study to appraise proposals for improving services to the Levenmouth area. This report sets out the results of a STAG Part 2 Appraisal of potential opportunities for improving public transport in the Levenmouth area.
E.2 Findings from the STAG Part 1 Appraisal
E.2.1 The STAG Part 1 Appraisal concluded that the rail-based options are the only measures which would meet all the planning objectives and the criteria set out in the Scottish Transport Appraisal Guidance (STAG). Consequently, the STAG Part 1 Appraisal recommended that consideration should be given to the following in the subsequent STAG Part 2 Appraisal:
E.3 Option Development
E.3.1 Further analysis of options and subsequent discussions with SEStran and Fife Council were carried out, after which two options for re-opening the line were identified for consideration:
E.3.2 Both Options would include rail freight facilities at Cameron Bridge. Option B would permit greater speeds than would be possible in option A, from a maximum of 40mph to 60mph, which is likely to encourage greater patronage and hence benefits.
E.3.3 In terms of actual train services and rail operating plans, the modelling and economic analysis assessed the extension of either of the existing hourly services from Kirkcaldy and Cowdenbeath, as well as extending both services.
E.4 Scheme Costs
E.4.1 Capital costs were estimated in 2008 Q2 prices and included allowances for contingencies, risk & uncertainty costs estimates and optimism bias costs estimates. These gave the following estimates:
E.4.2 Given that the project is unlikely to be open before 2015, it is worth presenting the anticipated final outturn costs for 2016. These have been estimated by applying the British construction industry projected inflation figures of approximately 6% per annum. This gave the following:
E.4.3 However, for the purposes of the economic evaluation, the current prices are used as per standard appraisal convention.
E.5 Findings from the STAG Part 2 Appraisal
E.5.1 The STAG Part 2 Appraisal identified the following conclusions:
E.6 Conclusions & Recommendations
E.6.1 Given the above appraisal results, the conclusions and recommendations are:
E.6.2 The implementation of the above recommendations should help progress the project forward and also provide further confidence to key stakeholders.